Russell Independent Campus
Project Description
Russell Independent Campus Wide HVAC Renovation. Trace Creek has recently completed the campus wide HVAC renovation at McDowell Intermediate, Russell Independent Primary School and Russell Independent High School. Nearly 140,000 SQF of HVAC renovation, all occupied by students and faculty. The project consist of converting the existing 2 pipe system to a new 4 pipe system, replacing all RTU’s, MAU’s, Boilers, FCU’S, Unit Ventilators and a new Building Automation System in it’s entirety. The project was based on a 9 month timeline, Trace Creek mobilized at the end of January. Covid-19 impacted this project heavily, pushing lead times back on equipment. Even with the constraints of the pandemic we we’re still able to finish the project by September, right on schedule for our 9 month completion date!